Former Tannery site redevelopment

In September, the City and Caleb Development Corporation closed on the sale of a 2.5 acre piece of the former Allied Leather site being sold by the City to Caleb for their new housing development. The sale price was $540,000 (which was the City’s full asking price). Phase I of Caleb’s development is scheduled for completion in September 2020, and features 34 housing units. It is anticipated that Phase II of the project will begin construction in 2021. You can see foundation working progressing now at the site.